Weeks 1 & 2
Excavation, form-work & casting of reinforced concrete strip foundation.
Weeks 3 & 4
Backfilling & preparation of slab areas and laying of water & electric services up from house.
Weeks 5 & 6
Backfilling trench for services, landscaping & laying of water drainage system to soak away.
Week 7
Casting of front concrete slab & Limecrete main slab.
Week 8
Building of flint-faced plinth wall, timber-frame for walls, and electric first fix.
Coming soon...